Campus Renovations
Location Changes
It’s an exciting time on campus! We began the renovation of the Mesa Building in April 2024. The renovation includes updates to improve the safety, technology, and interior look of the Mesa building. While living through the renovations will cause some inconveniences, we know it will be worth it in the end.
The renovation will be completed in four phases, with an estimated five months for each phase. The project began in April 2024 and is scheduled to be completed in Spring 2026.
- Phase I: 1st floor
- Phase II: 3rd floor
- Phase III: 2nd floor
- Phase IV: 4th floor
Temporary Office Relocations
Office | Current Location | Temporary Location |
---|---|---|
Admissions | MB 2215 | SAC 103 |
Bookstore | MB 1140 |
SAC 104 (Merchandise) S&T 2200 (Textbooks) |
Environmental Health & Safety | MB 1103 | Engineering 3.101 |
Financial Aid | MB 1225 | SAC Welcome Desk |
Food Pantry & Free Store | MB 1154 | Parker Ranch House |
Graduate Studies | MB 1208 | MB 4103 |
Human Resources | MB 1224 | Library 140B and Remote |
Police Department | MB 1240 | Not relocating |
Registrar’s Office | MB 1231 | SAC Welcome Desk |
Softball coaches | MB 1150 | Gym |
Student Accounts | MB 1220 | SAC Welcome Desk |
Testing Center | MB 1160 | MB 2117 (in Success Center) |
We understand the construction and these temporary office relocations may be an inconvenience. We appreciate your patience as we work to modernize the Mesa building, which will allow us to better serve our students and the region.